House
In the last few weeks, the house has come a long way! The interior paint is done, doors are all hung, the vinyl and laminate flooring are both done, the electrical is finished inside and out, all of the kitchen and bathroom cabinetry and counters are done, all the plumbing is installed, the kitchen appliances are installed, the tile is in, the air conditioner is installed, the water heater is installed, the rain gutters are up, and the lot is all graded out. Things look awesome! Coming next is grouting the tile, installing carpet, finishing the baseboards, finishing the HVAC vents, and landscaping. Other than that, all that's left is the clean up and touch ups. So we should be moving in in the next 2-3 weeks.